Midfield Terminal Building
Abu Dhabi, Emiratos Árabes Unidos
- X-shaped airport terminal building (Midfield Terminal Building MTB), situated between two runways, with capacity for 65 large aircraft
- 50 m high seven-storey central structure (Central Processor) with a total area of 700,000 m²
- 12,000 laborers at site working in shifts
- Scheduled opening in 2017 for up to 30 million passengers annually
TAV, Consolidated Contractors Company (CCC) and Arabtec Construction Joint Venture
Ubicación
El proyecto
Impresiones del proceso del proyecto.
The Midfield Terminal Complex is the ultimate in construction sites: in order to maintain the tight construction schedule, PERI planned and delivered the formwork and scaffolding systems, and has provided yet another convincing performance through the competent engineering service and provision of huge quantities of materials at short notice.
Over 6,000 PD 8 slab tables are in continuous use which is the equivalent to an area of almost 10 football pitches.
The massive beams are being constructed in one pour together with the slabs – with the help of strong load-bearing PD 8 slab tables and lightweight LIWA elements as side formwork.
Moveable PD 8 slab tables form the load-bearing sub-structure along the beams; for the slabs, MULTIFLEX girder slab formwork is used.
Easy lateral transport: the PD 8 slab tables can be moved by hand by means of a transportation trolley. This reduces crane requirements quite considerably.
PD 8 is the proven shoring system for slab tables and accommodates high loads. With only two different frame heights, almost any required height can be realized.
In order to process over 1,000 m³ every day, huge numbers of personnel and material are required.
For forming the up to 12.50 m high reinforced concrete walls, VARIO GT 24 girder wall formwork provides a maximum level of adaptability through the variable arrangement of lattice girders, steel walers and tie positions.
PERI is supporting the fast construction progress with over 6,000 slab tables as well as comprehensive formwork solutions, also for the walls and columns. As of 2017, up to 30 million passengers will be handled annually.
The Midfield Terminal Complex is the ultimate in construction sites: in order to maintain the tight construction schedule, PERI planned and delivered the formwork and scaffolding systems, and has provided yet another convincing performance through the competent engineering service and provision of huge quantities of materials at short notice.
Over 6,000 PD 8 slab tables are in continuous use which is the equivalent to an area of almost 10 football pitches.
The massive beams are being constructed in one pour together with the slabs – with the help of strong load-bearing PD 8 slab tables and lightweight LIWA elements as side formwork.
Moveable PD 8 slab tables form the load-bearing sub-structure along the beams; for the slabs, MULTIFLEX girder slab formwork is used.
Easy lateral transport: the PD 8 slab tables can be moved by hand by means of a transportation trolley. This reduces crane requirements quite considerably.
PD 8 is the proven shoring system for slab tables and accommodates high loads. With only two different frame heights, almost any required height can be realized.
In order to process over 1,000 m³ every day, huge numbers of personnel and material are required.
For forming the up to 12.50 m high reinforced concrete walls, VARIO GT 24 girder wall formwork provides a maximum level of adaptability through the variable arrangement of lattice girders, steel walers and tie positions.
PERI is supporting the fast construction progress with over 6,000 slab tables as well as comprehensive formwork solutions, also for the walls and columns. As of 2017, up to 30 million passengers will be handled annually.
Información del Proyecto
Estás trabajando en proyectos como este?
Llámenos al +56 2 2444 6000 para analizar más a fondo sus necesidades.